
Siesbach Süd wind farm: foundation work begins
Progress is clearly visible at the Siesbach South Wind Farm in the Birkenfeld district: the park infrastructure has been completed, and the next major construction phase is now underway. Foundation works for the wind turbines are scheduled to begin in mid-October 2026.
The project consists of three Enercon E-138 wind turbines, with commissioning planned for 2027. The wind farm is located south of Siesbach, a few kilometers west of Idar-Oberstein.
Current Status of Foundation Works (Status: 05 November 2026)
-S-01: Foundation successfully poured and completed.
-S-02: Concrete pouring scheduled for 10 November 2026.
-S-03: Concrete pouring scheduled for 17 November 2026.
On the concrete pouring days, increased traffic can be expected along the transport routes between 06:00 and 22:00. The safety of local residents remains our highest priority. Together with the logistics companies involved, we are placing particular emphasis on considerate driving practices, especially during the early morning and evening hours. In addition, traffic movements at selected locations will be coordinated by traffic marshals to ensure safe and orderly operations.
We would like to thank all residents for their understanding during this temporary but important phase of construction. Further updates on the project’s progress will be provided here on a regular basis.



